Ahs Vegetated Wall System2020-02-25T08:46:24+00:00
Loading...

Woven Bag

We use a permeable needle punched, non-woven geotextile to make our bags. The material is heat bonded on all sides to help maintain the bag’s shape when filled. The geotextile is UV stabilised, ensuring the bags do not rot.

Bag size when filled: 300mm wide x 750mm long x 140mm high.

Generally 14 bags per m2 (tie back method).

Polypropylene Plate

The plate is manufactured by injection moulding using talc filled polypropylene and uses wholly sourced recycled material.

The result is a consistently high-quality product that has great resistance to naturally found alkalis and acids within the ground and exhibits high fatigue resistance.

Size: 330mm long x 100mm wide x 42mm high – with 11 spikes.

Specification

Paving Grid
  • Talc-filled polypropylene: 74gm
  • Density: 0.98G/cc
  • Tensile strength: 28MPa
  • Elongation at break: 40%
  • Modulus: = 1.8GPa
  • Notched Izod: = 1.2j/cm
  • Melting point: = 157°C.

Installation Guide

PAVING GRID WITH GRASS INFILL

PAVING GRID WITH GRASS INFILL

01

The existing subsoil/base (F) should first be tested to determine strength and permeability. Excavate/level the subsoil/base in preparation for the laying procedure as detailed below.

02

Cover the subsoil with a layer of Geotextile Membrane (E).

03

Apply an open grade sub-base (D). Drainage may be required if subsoil has poor permeability. The depth of this sub-base will depend on the strength and permeability of the existing subsoil. For the purpose of these installation guidelines, we have assumed a CBR strength of the subsoil of 2-4, which requires a sub-base depth of 150-225mm. If the strength of the subsoil is deemed to be lower than this, the depth of the sub-base will need to be increased accordingly. It is essential that the sub-base is compacted with a vibrating roller or vibrating plate.

04

Apply a bedding layer of 50-70mm (C) of 60-40 or 70-30 root zone. The bedding layer must be compacted.

05

Apply AHS Paving Grid (B). Fill the grid with more of the root zone, to within 3mm of the surface of the grid. Do not overfill the paving cells.

06

A vibrating plate can then be used to firm the grid and root zone infill.

07

The area can now be seeded and watered. Do not overfill the paving cells.

08

The seeded area can be driven on immediately. However, we strongly recommend that you allow time for root establishment before using it. Watering is essential during the early days/weeks of establishment, especially during times of exceptionally hot weather.

09

Edging and/or kerbing should be used with AHS Paving Grid to prevent lateral movement and ensure the grid is able to withstand pressure from vehicular and pedestrian use. 10 Maximum recommended gradient for vehicular use is 11°.

Contact Us

Error: Contact form not found.

ISO 9001 Certified
FSC-certified
ISO 9001 Certified
constructionline logo
BALI Registered
Go to Top